| Meeting date |
May 9, 2001 |
Task |
Person in Charge |
|
| One year |
May 9, 2000 |
Summarize results of overall and
inidivual session surveys from previous meeting |
|
| 6 months |
November 10, 2000 |
Contact office contacts and
prepare attendee list. Create group
mailing list for email |
|
| 6 months |
November 10, 2000 |
Site visit to resort. |
|
| 5 months |
December 10, 2000 |
Survey attendees for topic ideas
and interest |
|
| 5 months |
December 10, 2000 |
Prepare preliminary agenda and
events. Send to coordinator. |
|
| 4 months |
January 9, 2001 |
Compile list of topics and make
session recommendations to Session Chair (SC) |
|
| 4 months |
January 9, 2001 |
Get SC approval for topics,
agenda, events. |
|
| 4 months |
January 9, 2001 |
Confirm activities and events. |
|
| 3 months |
February 8, 2001 |
Confirm session chairs and
request session descriptions |
|
| 3 months |
February 8, 2001 |
Contact
outside speakers and confirm dates, fee and expense arrangements. |
|
| 3 months |
February 8, 2001 |
Prepare final agenda, sessions
and descriptions |
|
| 3 months |
February 8, 2001 |
Develop signup database. |
|
| 3 months |
February 8, 2001 |
Office staff conference call to
discuss meeting and schedule. |
|
| 2 months |
March 10, 2001 |
Send registration database to
attendees. |
|
| 2 months |
March 10, 2001 |
Design program and collateral
materials. |
|
| 2 months |
March 10, 2001 |
Send message to speakers
regarding handouts and AV requests. |
|
| 1 month |
April 9, 2001 |
Confirm all meeting space and
meal locations for program. |
|
| 1 month |
April 9, 2001 |
Develop session survey forms to
include in program. Overall session
evaluation will be done on Notes. |
|
| 1 month |
April 9, 2001 |
Develop archive and survey
database. |
|
| 1 month |
April 9, 2001 |
Send attendee list and agenda to
Communications to make signs and nametags. |
|
| 3 weeks |
April 18, 2001 |
Request travel information. |
|
| 3 weeks |
April 18, 2001 |
Send all banquet and event
orders, meeting resume and flight manifest to hotel and DMC. |
|
| 1 week |
May 2, 2001 |
Ship supplies, programs,
nametags, signs, handouts to hotel. |
|
| Post meeting |
|
Review evaluations and write
meeting summary. |
|
| Post meeting |
|
Prepare estimate budget for
meeting. |
|
| Post meeting |
|
Review final costs and prepare
budget report for SC. |
|
|
|
|
|
|
|